eco-power innovation

RUN-OF-RIVER HYDROELECTRICITY

How Run-of-River Works

Run-of-River (ROR) hydro-electric systems harvest the energy from flowing water to generate clean electricity. The 60-MW COHECO powerplant harnesses power from the natural flow rate of the Amburayan river.

To generate clean electricity, a seven-meter high weir gathers water and lets it flow into a tunnel. The river continues to run its natural course even as the water in the tunnel powers turbines to generate clean energy—without emitting carbon.

70% of total manpower
sourced locally
Forecasted energy generation:
298.7 GWh per year
To power 124,000
households*
*based on ave. household consumption of 200KWh/month or 2,400KWh/year

Advantages of Run-of-River Systems

Cleaner power.

ROR harnesses the natural potential energy and flow rate of water, generating electricity without burning coal or natural gas, which means fewer greenhouse gas emissions.

Natural flow.

ROR uses the river’s natural flow, and does not need a reservoir. Because the Amburayan River is surrounded by steep mountain banks, the river’s rise during the rainy season is a naturally occurring event.

Smaller footprint.

The 60-MW of power we generate uses only the river’s natural flow, and does not emit carbon. Our equipment and structures were chosen to have the least impact on the environment. Working with TAWID Foundation, we ensured that the existing flora and fauna were minimally impacted and that the eco-system in our area was largely undisturbed.

Faster cost recovery.

Compared to other sources of energy, investments in ROR systems can be recovered faster, due to lower costs and shorter development times.

Project Timeline

Old Developer timeline

Pronimbus Timeline

2019
Jul 16

2015

October 2015

  • EMB/DENR Environmental Compliance Certificate (ECC) – La Union.

November 2015

  • DENR Special Land Use Permit (SLUP)
  • November 2015 DENR Tree-cutting Permit
December 2015

  • Introduction of EPC Contractor – GHCB
  • Introduction of owner’s engineer – KECC
Jul 16

2016

February 2016

  • Start of right-of-way activities – COHECO
  • Project Management Plan – COHECO

April 2016

  • NCIP Certification Pre-condition – La Union
Jul 16

2017

April/May 2017

  • Access Road alignment by EPC Cont.

May 2017

  • Start of clearing and grubbing activities
July 2017

  • DENR Forest Land Use Agreement (FLAg) – Benguet and La Union

August 2017

  • EMB Cease and Desist Order (CDO)

September 2017

  • Legal opinion on CLOA lots – DAR Central

December 2017

  • Replaced owner’s engineer – GHD

January 2018

  • Temporary lifting of CDO – EMB
Jul 16

2018

February 2018

  • Replacement of EPC contractor – SCIC

April 2018

  • Final alignment of transmission line – NGCP
  • Continuation of CDMP for amendment
June 2018

  • System Impact Study (SIS) – NGCP
NGCP Conn. Agr. ongoing

October 2018

  • Amendment of FLAg applications

November 2018

  • EPC contract termination
Jul 16

2019

(ongoing)

Questions and inquiries?

Contact us today.

Let’s wield a new kind of energy: to power, and empower.



Back to Top